CountyGA
Posted
Aug 17, 2026
Nov 4, 2026
Stewart Mill Road at Bermuda Road Roundabout (12 Months) RFP
Work consist of 100 tn of recycled asphalt concrete patching, incl bituminous material & h lime, 190 tn of recycled asphalt concrete leveling, incl bituminous material & h lime, 320 tn of recycled asphalt concrete 12. 5 mm superpave, gp 2 only, incl bituminous material & h lime, 780 tn of recycled asphalt concrete 25 mm superpave, gp 1 or 2, incl bituminous material & h lime, 370 tn of recycled asphalt concrete 19 mm superpave, gp 1 or 2,incl bitum material & h lime, 53 tn of recycled asphalt concrete 12. 5 mm superpave, gp 2 only, incl polymer modified bituminous material & h lime, 110 sy of mill asphalt concrete pavement, 97 sy of driveway concrete.